bridge damageThe Colorado Department of Transportation along with contractor Kraemer North America, will begin emergency repairs to a portion of the Sky Ridge Avenue Bridge over I-25 between Ridgegate Parkway and Lincoln Avenue. These repairs will involve removing a portion of the structure and completely replacing it with a new girder and bridge deck.

This work will require several overnight I-25 closures with major traffic impacts through June. In advance of the work, CDOT will close an auxiliary lane between Ridgegate Parkway and Lincoln Avenue on Wednesday, May 19 for staging equipment, which may cause some minor delays during peak travel periods.

All work is scheduled to be completed prior to the Fourth of July holiday weekend.

Full closures in June:

Full Overnight closures of northbound I-25 from Ridgegate Parkway to Lincoln Avenue, along with double left lane closures on southbound I-25:

  • Friday night, June 4, from 9 p.m. to 5 a.m. Delays could be up to 20 minutes. Lanes will be open during the day.
  • Saturday night, June 5 from 7 p.m. to 1 p.m. Sunday, June 6. The closures are necessary for bridge demolition work. Motorists should avoid this area if possible. Extreme delays are likely, of up to 2 hours through Sunday afternoon.
  • Overnight Sunday, June 6 to Saturday, June 12 from 9 p.m. to 5 a.m. Work on these nights involves bridge replacement, including setting a new girder and installing deck panels.
  • Overnight Tuesday, June 15 and Thursday, June 24, from 9 p.m. to 5 a.m., full closures of northbound I-25 to complete the repairs by pouring the concrete deck. All lanes on southbound I-25 will be open.

When overnight northbound I-25 closures are not in place, there may be nighttime single and double lane closures on northbound and southbound I-25 between Ridgegate Parkway and Lincoln Avenue during June.

Detour: northbound I-25 traffic will use Exit 192/ Ridgegate Parkway and turn right. Continue to Peoria Street and turn left. Proceed on Peoria Street to Lincoln Avenue and turn left. Continue on Lincoln Avenue to the northbound I-25 on-ramp. (Pictured below)

The schedule above is subject to change depending on the weather and other unforeseen circumstances.

detour

For more information, click here. For questions or concerns, contact the Project/study Information Hotline at 720-770-0353 or via e-mail at [email protected].